Ensure the facility provides enough vertical clearance for the full lifting travel of 1,800 mm plus the vehicle height. Critical Safety & Operating Procedures
A pre-use inspection list that every operator must sign off on. Includes checking hydraulic hoses for leaks, ensuring the load hook is not deformed, and verifying that the synchronization cable between columns is intact. hofmann duolift gte 2500 manual
Lubricate the main lifting screws using high-performance spindle grease. Visually check for any oil leaks or unusual motor noises. Monthly Tasks Check the wear dimension of the safety load nut. Inspect electrical cables for fraying or damage. Tighten column anchor bolts to check for floor shifting. Safety Wear Nut Check Ensure the facility provides enough vertical clearance for
Position the lift support pads (diameter 120 mm) at the manufacturer's recommended lifting points on the vehicle. Inspect electrical cables for fraying or damage